October 2024
- Solar Array
- On-going civil activities within the fence line of the solar array area, inclusive of initial drain tile re-routing and installation.
- On-going access road entrance installation throughout the project site.
- On-going material deliveries.
- Substation/Transmission Line
- Delivery of major electrical equipment at the project substation.
- Completion of transmission line pole erection.
- On-going above/below ground electrical work.
September 2024
- Solar Array
- Contractor mobilization
- Installation of construction trailers for site personnel (east of RT 739, south of Evans Road).
- Installation of main material laydown yard (east of RT 739, south of Evans Road).
- Installation of Stormwater Management control features throughout the project site.
- Substation/Transmission Line
- Completion of transmission line pole foundation installation.
- Completion of substation structural foundation installation.
- Installation of transmission line poles and ongoing electrical work at the project substation.
- Initial delivery of major electrical equipment at the project substation.
August 2024
- Substation/Transmission Line
- On-going transmission line structural foundation installation.
- On-going structural foundation install at the project substation.
July 2024
- Substation/Transmission Line
- Completion of civil grading activities at the project substation.
- Commencement of substation structural foundation installation.
- Commencement of transmission line pole foundation drilling and installation.
June 2024
- Substation/Transmission Line
- On-going civil grading and access road installation at the project substation.
May 2024
- Substation/Transmission Line
- Contractor mobilization
- Commencement of civil work at the project substation.